170 Ind. Admin. Code 4-6-11

Current through December 4, 2024
Section 170 IAC 4-6-11 - Ratemaking treatment; initial application proceedings

Authority: IC 8-1-2-6.6

Affected: IC 8-1-2; IC 8-1-8.5; IC 8-1-8.7; IC 8-1-27; IC 8-1.5-3-8

Sec. 11.

The commission shall grant ratemaking treatment to qualified pollution control property under construction eligible for ratemaking treatment under IC 8-1-2-6.6, as provided in section 10 of this rule, on petition by a utility under IC 8-1-2-61 or at the request of a utility in any of the following:

(1) A proceeding involving the utility's base rates and charges or an adjustment to its rates, charges, or rate structures, except for a fuel cost adjustment proceeding under IC 8-1-2-42(d).
(2) A review proceeding under IC 8-1-8.5 or IC 8-1-8.7. The commission may grant ratemaking treatment under this section only for construction of qualified pollution control property associated with the generating facility or clean coal technology project under review.
(3) A review proceeding under IC 8-1-27.

170 IAC 4-6-11

Indiana Utility Regulatory Commission; 170 IAC 4-6-11; filed Oct 5, 1993, 5:00 p.m.: 17 IR 178; readopted filed Jul 11, 2001, 4:30 p.m.: 24 IR 4233; readopted filed Apr 24, 2007, 8:21 a.m.: 20070509-IR-170070147RFA; readopted filed Aug 2, 2013, 2:16 p.m.: 20130828-IR-170130227RFA
Readopted filed 4/11/2019, 9:04 a.m.: 20190508-IR-170190136RFA