Section 170 IAC 4-5-9 - Testing of submeters prior to installation

Authority: IC 8-1-1-3; IC 8-1-2-36.5

Affected: IC 8-1-2-36.5

Sec. 9.

Tests of Submeters Prior to Installation. No submeter shall be placed in service unless its accuracy has been established. If any submeter is removed from actual service and replaced by another submeter for any purpose whatsoever, it shall be properly tested and adjusted before being placed in service again.

170 IAC 4-5-9

Indiana Utility Regulatory Commission; 170 IAC 4-5-9; filed Dec 13, 1984, 3:13 pm: 8 IR 487, eff Jan 1, 1985 [IC 4-22-2-5 suspends the effectiveness of a rule document for thirty 30 days after filing with the Secretary of State. LSA Document #84-57(F) was filed Dec 13, 1984.]; readopted filed Jul 11, 2001, 4:30 p.m.: 24 IR 4233; readopted filed Apr 24, 2007, 8:21 a.m.: 20070509-IR-170070147RFA; readopted filed Aug 2, 2013, 2:16 p.m.: 20130828-IR-170130227RFA