170 Ind. Admin. Code 4-10-2

Current through December 4, 2024
Section 170 IAC 4-10-2 - Applicability under IC 8-1-40.5

Authority: IC 8-1-1-3; IC 8-1-40.5-19

Affected: IC 8-1-40.5-3; IC 8-1-40.5-10

Sec. 2.

This rule applies to an electric utility, as defined under IC 8-1-40.5-3, meeting the threshold for qualified costs under IC 8-1-40.5-10(a).

170 IAC 4-10-2

Indiana Utility Regulatory Commission; 170 IAC 4-10-1; emergency rule filed 12/20/2021, 9:30 a.m.: 20211229-IR-170210538ERA, eff 1/1/2022
Filed 8/6/2024, 12:06 p.m.: 20240904-IR-170240090FRA