170 Ind. Admin. Code 4-10-1

Current through December 4, 2024
Section 170 IAC 4-10-1 - Policy and scope

Authority: IC 8-1-1-3; IC 8-1-40.5-19

Affected: IC 8-1-40.5

Sec. 1.

This rule is intended to establish procedures and guidelines for cost securitization for retired electric utility assets under IC 8-1-40.5.

170 IAC 4-10-1

Indiana Utility Regulatory Commission; 170 IAC 4-10-1; emergency rule filed 12/20/2021, 9:30 a.m.: 20211229-IR-170210538ERA, eff 1/1/2022
Filed 8/6/2024, 12:06 p.m.: 20240904-IR-170240090FRA