The following requirements apply to all electrical generators used to provide electrical power to any nonmetallic mineral processing plant. The requirements apply to each site of operations.
Rated Output Capacities (kW) | Allowable Operating Hours (hr/day) | Allowable Operating Hours (hr/yr) | ||
Attainment Unclassifiable Areas | PM-10 Nonattainment Areas | Attainment Unclassifiable Areas | PM-10 Nonattainment Areas | |
0 - 454 | 24 | 8 | 8760 | 2880 |
455 - 1000 | 24 | 24 | 8760 | 8760 |
1001 - 2000 | 24 | 24 | 5200 | 5200 |
kW = kilowatts hr/day = hours per day hr/yr = hours per year |
Idaho Admin. Code r. 58.01.01.798