Current through November, 2024
Section 15-36-06 - Permit plan application processing; estimated fees(a) Following the pre-application conference, the applicant shall submit to the energy resources coordinator, in a manner allowed by the coordinator, a request for renewable energy facility permit plan application processing. The request shall include information deemed necessary by the coordinator and facilitator in the pre-application conference to determine the fees to be incurred in processing the application and overseeing the permit plan process.(b) The coordinator shall inform the applicant of the estimated fee amount and, upon the applicant's acceptance of the amount, the coordinator shall require the applicant to make periodic payments of such fees pursuant to a cost reimbursement agreement. Fees are discussed in more detail in subchapter 4.(c) Should the applicant file amendments or supplements to the application or should the coordinator find that additional study for the application is required, additional fee estimates shall be prepared by the coordinator, and the applicant shall be advised of the additional fees.[Eff. JUL 01 2010] (Auth: HRS § 201N-12) (Imp: HRS § 201N-4)