Strike Section 406.1 of the International Green Construction Code in its entirety and insert new Section 406.1 in the Green Construction Code in its place to read as follows:
Building site waste management requirements. Not less than 75 percent of the land-clearing debris from a building site shall be diverted from landfills. Land-clearing debris includes rock, trees, stumps and associated vegetation. The building site development shall comply with the following additional requirements:
Insert a new Section 406.3 in the Green Construction Code to read as follows:
Verification. Prior to issuance of the first certificate of occupancy for occupiable space in a story above grade plane, or prior to final inspection, if a new certificate of occupancy is not required, t he Department is authorized to require the owner, contractor or an approved agency to provide verification of the project's compliance with Section 406.1.
D.C. Mun. Regs. tit. 12, r. 12-K406