49 C.F.R. § 633.23

Current through September 30, 2024
Section 633.23 - FTA review of a project management plan

Within 60 days of receipt of a project management plan, the Administrator will notify the recipient that:

(a) The plan is approved;
(b) The plan is disapproved, including the reasons for the disapproval;
(c) The plan will require modification, as specified, before approval; or
(d) The Administrator has not yet completed review of the plan, and state when it will be reviewed.

49 C.F.R. §633.23

85 FR 59679, 10/23/2020