The determination on whether or not to hold a scoping meeting will depend on the same circumstances and factors as for the holding of public hearings under § 58.59 . The responsible entity must wait at least 15 days after disseminating or publishing the NOI/EIS before holding a scoping meeting.
24 C.F.R. §58.56