Responsible and Trustee Agencies, and the Office of Planning and Research shall provide a response to a Notice of Preparation to the Lead Agency within 30 days after receipt of the notice. If they fail to reply within the 30 days with either a response or a well justified request for additional time, the lead agency may assume that none of those entitles have a response to make and may ignore a late response.
Cal. Code Regs. Tit. 14, § 15103
2. Change without regulatory effect amending section and NOTE filed 10-6-2005 pursuant to section 100, title 1, California Code of Regulations (Register 2005, No. 40).
Note: Authority cited: Section 21083, Public Resources Code. Reference: Section 21080.4, Public Resources Code.
2. Change without regulatory effect amending section and Note filed 10-6-2005 pursuant to section 100, title 1, California Code of Regulations (Register 2005, No. 40).