The lead agency shall determine within 30 days after accepting an application as complete whether it intends to prepare an EIR or a negative declaration or use a previously prepared EIR or negative declaration except as provided in Section 15111. The 30 day period may be extended 15 days upon the consent of the lead agency and the project applicant.
Cal. Code Regs. Tit. 14, § 15102
2. Change without regulatory effect amending NOTE filed 10-6-2005 pursuant to section 100, title 1, California Code of Regulations (Register 2005, No. 40).
Note: Authority cited: Section 21083, Public Resources Code. Reference: Section 21080.2, Public Resources Code.
2. Change without regulatory effect amendingNote filed 10-6-2005 pursuant to section 100, title 1, California Code of Regulations (Register 2005, No. 40).