Ariz. Admin. Code § 18-15-825

Current through Register Vol. 30, No. 50, December 13, 2024
Section R18-15-825 - Remedies by the Authority
A. If the Authority sustains a protest in whole or part and determines that a Solicitation, a determination of not susceptible for Award, or Contract Award does not comply with the Procurement statutes and regulations, the Authority shall implement an appropriate remedy.
B. In determining an appropriate remedy, the Authority shall consider all the circumstances surrounding the Procurement or proposed Procurement including:
1. The seriousness of the Procurement deficiency;
2. The degree of prejudice to other interested parties or to the integrity of the Procurement system;
3. The good faith of the parties;
4. The extent of performance;
5. The costs to the Authority;
6. The urgency of the Procurement;
7. The impact on the agency's mission; and
8. Other relevant issues.
C. The Authority may implement any of the following appropriate remedies:
1. Decline to exercise an option to renew under the Contract;
2. Terminate the Contract;
3. Amend the Solicitation;
4. Issue a new Solicitation;
5. Award a Contract consistent with this Article; or
6. Render such other relief as determined necessary to ensure compliance with this Article.

Ariz. Admin. Code § R18-15-825

New Section made by final expedited rulemaking at 30 A.A.R. 806, effective 4/3/2024.