Ariz. Admin. Code § 14-2-2628

Current through Register Vol. 30, No. 50, December 13, 2024
Section R14-2-2628 - Interconnection Manuals
A. No later than 90 calendar days after the effective date of this Article, each Utility shall file with Docket Control, for Commission review and approval, an Interconnection Manual that:
1. Contains detailed technical, safety, and protection requirements necessary to interconnect a Generating Facility to the Distribution System in compliance with this Article and Good Utility Practice; and
2. Specifies by date, either within its main text or in an appendix, the version of each standard, code, or guideline with which an Applicant's Generating Facility must comply to be eligible for Interconnection and Parallel Operation.
B. A Utility shall revise its Interconnection Manual as necessary to ensure compliance with Good Utility Practice.
C. A Utility shall file each revision to its Interconnection Manual with Docket Control, for Commission review and approval, at least 60 calendar days prior to the proposed effective date of the revision.
D. A revision to an Interconnection Manual that a Utility has determined is necessary to enhance health or safety shall become effective immediately, subject to subsequent review and approval by the Commission.
E. The Commission's Utilities Division may contest a Utility's proposed revision to its Interconnection Manual and may seek a suspension of the effective date of the revision to allow for further review.
F. A Utility shall file with Docket Control, within 10 calendar days after the effective date of a decision approving any revisions to its Interconnection Manual, an updated Interconnection Manual conforming to the Commission's decision.
G. A Utility shall make its Interconnection Manual available on the Utility's website.
H. A Utility shall implement and ensure compliance with its Commission-approved Interconnection Manual.

Ariz. Admin. Code § R14-2-2628

Adopted by final rulemaking at 26 A.A.R. 473, effective 2/25/2020.