Ariz. Admin. Code § 14-2-2627

Current through Register Vol. 30, No. 50, December 13, 2024
Section R14-2-2627 - Electric Cooperatives
A. Upon Commission approval of an Electric Cooperative's Interconnection Manual, its provisions shall substitute for the timeline requirements set forth in R14-2-2614 and R14-2-2616 through R14-2-2623 for the Electric Cooperative and its Customers.
B. Each Electric Cooperative shall employ best reasonable efforts to comply with the deadlines set forth in the applicable provisions of this Article or, if unable to meet those deadlines, shall process all Applications and conduct all inspections and tests in the shortest time practical.

Ariz. Admin. Code § R14-2-2627

Adopted by final rulemaking at 26 A.A.R. 473, effective 2/25/2020.