Section R12-7-135 - Gas-oil Ratio and Potential Tests
A. Each operator shall conduct a gas-oil ratio test between 5 and 15 days after the completion or recompletion of any well located in a pool which contains both oil and gas. The average daily oil production, the average daily gas production, and the average gas-oil ratio shall be recorded.
B. The results of the gas-oil ratio test shall be reported in writing to the Commission within 15 days after completion of the test.
C. Each operator shall conduct a potential test within 30 days following the completion or recompletion of any well for the production of oil. The results of this test shall be reported in writing to the Commission within 15 days after completion of the test.