Current through October 17, 2024
Section 18 AAC 60.245 - Prompt closure(a) Except where a different time is specified in 18 AAC 60.395(f) or is otherwise approved by the department, the owner or operator of a landfill shall place the final cover on those waste management areas that have reached final elevation within 90 days after the last waste placement.(b) The requirements of this section do not apply to an inactive drilling waste disposal site.Eff. 1/28/96, Register 137Authority:AS 44.46.020