Consistent with the requirements of the Secretary of Defense, the Secretary of Energy shall ensure that the nuclear security enterprise-
Not later than March 1, 2015, and each year thereafter through 2030, the Secretary of Energy shall certify to the congressional defense committees and the Secretary of Defense that the programs and budget of the Secretary of Energy will enable the nuclear security enterprise to meet the requirements under subsection (a).
If the Secretary of Energy does not make a certification under subsection (b) by March 1 of any year in which a certification is required under that subsection, by not later than May 1 of such year, the Chairman of the Nuclear Weapons Council shall submit to the congressional defense committees a plan to enable the nuclear security enterprise to meet the requirements under subsection (a). Such plan shall include identification of the resources of the Department of Energy that the Chairman determines should be redirected to support the plan to meet such requirements.
Not later than 30 days after the date on which a covered project achieves a critical decision milestone, the Assistant Secretary for Environmental Management and the Deputy Administrator for Defense Programs shall jointly certify to the congressional defense committees that the operations, infrastructure, and workforce of such project are adequate to carry out the delivery and disposal of planned waste shipments relating to the plutonium enterprise, as outlined in the critical decision memoranda of the Department of Energy with respect to such project.
If the Assistant Secretary for Environmental Management and the Deputy Administrator for Defense Programs fail to make a certification under paragraph (1) by the date specified in such paragraph with respect to a covered project achieving a critical decision milestone, the Assistant Secretary and the Deputy Administrator shall jointly submit to the congressional defense committees, by not later than 30 days after such date, a plan to ensure that the operations, infrastructure, and workforce of such project will be adequate to carry out the delivery and disposal of planned waste shipments described in such paragraph.
Not later than March 1 of each year during the period beginning on the date on which the first covered project achieves critical decision 2 in the acquisition process and ending on the date on which the second project achieves critical decision 4 and begins operations, the Administrator for Nuclear Security shall submit to the congressional defense committees a report on the planned production goals of both covered projects during the first 10 years of the operation of the projects.
Each report under paragraph (1) shall include-
Until the date on which the Administrator certifies to the congressional defense committees that the base capability to produce not less than 30 war reserve plutonium pits per year has been established at Los Alamos National Laboratory, the Administrator may not-
Paragraph (1) shall not apply with respect to-
In this subsection:
In this subsection, the term "covered project" means-
Not later than 570 days after December 22, 2023, the Administrator for Nuclear Security shall ensure that the plutonium modernization program established by the Office of Defense Programs of the National Nuclear Security Administration, or any subsequently developed program designed to meet the requirements under subsection (a), is managed in accordance with the best practices for schedule development and cost estimating of the Government Accountability Office.
50 U.S.C. § 2538a
EDITORIAL NOTES
REFERENCES IN TEXTDecember 22, 2023, referred to in subsec. (f)(1)(A), (2)(A), was in the original "the date of the enactment of this Act" and was translated as referring to the date of enactment of Pub. L. 118-31, which enacted subsec. (f).
AMENDMENTS2023-Subsecs. (f), (g). Pub. L. 118-31, §3116, added subsec. (f) and redesignated former subsec. (f) as (g). Subsec. (h). Pub. L. 118-31, §3117, added subsec. (h). 2021-Subsecs. (d) to (f). Pub. L. 117-81 added subsecs. (d) to (f).2019-Subsec. (a)(5). Pub. L. 116-92, §3116(b)(1), added par. (5) and struck out former par. (5) which read as follows: "during a pilot period of not less than 90 days during 2027 (subject to subsection (b)), demonstrates the capability to produce war reserve plutonium pits at a rate sufficient to produce 80 pits per year." Subsec. (b). Pub. L. 116-92, §3116(b)(2) -(4), redesignated subsec. (c) as (b), substituted "2030" for "2027 (or, if the authority under subsection (b) is exercised, 2029)", and struck out former subsec. (b) which authorized a two-year delay of the demonstration requirement. Subsec. (c). Pub. L. 116-92, §3116(b)(3), (5), redesignated subsec. (d) as (c) and substituted "subsection (b)" for "subsection (c)". Former subsec. (c) redesignated (b).Subsec. (d). Pub. L. 116-92, §3116(b)(3), redesignated subsec. (d) as (c).
STATUTORY NOTES AND RELATED SUBSIDIARIES
CERTIFICATION OF COMPLETION OF MILESTONES WITH RESPECT TO PLUTONIUM PIT AGING Pub. L. 117-263, §3124, 136 Stat. 3057, provided that: "(a) REQUIREMENT.-The Administrator for Nuclear Security shall complete the milestones on plutonium pit aging identified in the report entitled 'Research Program Plan for Plutonium and Pit Aging', published by the National Nuclear Security Administration in September 2021. "(b) ASSESSMENTS.-The Administrator shall-"(1) acting through the Defense Programs Advisory Committee, conduct biennial reviews during the period beginning not later than one year after the date of the enactment of this Act [Dec. 23, 2022] and ending December 31, 2030, regarding the progress achieved toward completing the milestones described in subsection (a); and"(2) seek to enter into an arrangement with the private scientific advisory group known as JASON to conduct, not later than 2030, an assessment of plutonium pit aging."(c) BRIEFINGS.-During the period beginning not later than one year after the date of the enactment of this Act and ending December 31, 2030, the Administrator shall provide to the congressional defense committees [Committees on Armed Services and Appropriations of the Senate and the House of Representatives] biennial briefings on-"(1) the progress achieved toward completing the milestones described in subsection (a); and "(2) the results of the assessments described in subsection (b)."(d) CERTIFICATION OF COMPLETION OF MILESTONES.-Not later than October 1, 2031, the Administrator shall-"(1) certify to the congressional defense committees whether the milestones described in subsection (a) have been achieved; and"(2) if the milestones have not been achieved, submit to such committees a report-"(A) describing the reasons such milestones have not been achieved;"(B) including, if the Administrator determines the Administration will not be able to meet one of such milestones, an explanation for that determination; and"(C) specifying new dates for the completion of the milestones the Administrator anticipates the Administration will meet."
AUTHORIZATION OF WORKFORCE DEVELOPMENT AND TRAINING PARTNERSHIP PROGRAMS WITHIN NATIONAL NUCLEAR SECURITY ADMINISTRATION Pub. L. 117-263, §3126, 136 Stat. 3058, provided that:"(a) AUTHORITY.-The Administrator for Nuclear Security may authorize management and operating contractors at covered facilities to develop and implement workforce development and training partnership programs to further the education and training of employees or prospective employees of such management and operating contractors to meet the requirements of section 4219 of the Atomic Energy Defense Act (50 U.S.C. 2538a)."(b) CAPACITY.-To carry out subsection (a), a management and operating contractor at a covered facility may provide funding through grants or other means to cover the costs of the development and implementation of a workforce development and training partnership program authorized under such subsection, including costs relating to curriculum development, hiring of teachers, procurement of equipment and machinery, use of facilities or other properties, and provision of scholarships and fellowships."(c) DEFINITIONS.-In this section: "(1) The term 'covered facility' means-"(A) Los Alamos National Laboratory, Los Alamos, New Mexico; or"(B) the Savannah River Site, Aiken, South Carolina."(2) The term 'prospective employee' means an individual who has applied (or who, based on their field of study and experience, is likely to apply) for a position of employment with a management and operating contractor to support plutonium pit production at a covered facility."
SENSE OF CONGRESS RELATED TO MODIFICATION TO CERTAIN REQUIREMENTS RELATING TO PLUTONIUM PIT PRODUCTION CAPACITY Pub. L. 116-92, §3116, 133 Stat. 1951, provided that: "It is the sense of Congress that- "(1) rebuilding a robust plutonium pit production infrastructure with a capacity of up to 80 pits per year is critical to maintaining the viability of the nuclear weapons stockpile; "(2) that effort will require cooperation from experts across the nuclear security enterprise; and"(3) any further delay to achieving a plutonium sustainment capability to support the planned stockpile life extension programs will result in an unacceptable capability gap to our deterrent posture."
- Administration
- The term "Administration" means the National Nuclear Security Administration.
- Administrator
- The term "Administrator" means the Administrator for Nuclear Security.
- Nuclear Weapons Council
- The term "Nuclear Weapons Council" means the Nuclear Weapons Council established by section 179 of title 10.
- congressional defense committees
- The term "congressional defense committees" means-(A) the Committee on Armed Services and the Committee on Appropriations of the Senate; and(B) the Committee on Armed Services and the Committee on Appropriations of the House of Representatives.
- nuclear security enterprise
- The term "nuclear security enterprise" means the physical facilities, technology, and human capital of the national security laboratories and the nuclear weapons production facilities.