In this section:
The term "capacity contract" means a contract entered into by the Secretary and an eligible entity under subsection (e)(1)(A) for the right to the use of the transmission capacity of an eligible project.
The term "eligible electric power transmission line" means an electric power transmission line that is capable of transmitting not less than-
The term "eligible entity" means an entity seeking to carry out an eligible project.
The term "eligible project" means a project (including any related facility)-
The term "Fund" means the Transmission Facilitation Fund established by subsection (d)(1).
The term "program" means the Transmission Facilitation Program established by subsection (b).
The term "related facility" means a facility related to an eligible project described in paragraph (4).
The term "related facility" does not include-
There is established a program, to be known as the "Transmission Facilitation Program", under which the Secretary shall facilitate the construction of electric power transmission lines and related facilities in accordance with subsection (e).
To be eligible for assistance under this section, an eligible entity shall submit to the Secretary an application at such time, in such manner, and containing such information as the Secretary may require.
The Secretary shall establish procedures for the solicitation and review of applications from eligible entities.
There is established in the Treasury a fund, to be known as the "Transmission Facilitation Fund", consisting of-
The Secretary of the Treasury may, without further appropriation and without fiscal year limitation, loan to the Secretary on such terms as may be fixed by the Secretary and the Secretary of the Treasury, such sums as, in the judgment of the Secretary, are from time to time required for the purpose of carrying out the program, not to exceed, in the aggregate (including deferred interest), $2,500,000,000 in outstanding repayable balances at any 1 time.
There is authorized to be appropriated to the Secretary to carry out the program, including for any administrative expenses of carrying out the program that are not recovered under paragraph (4), $10,000,000 for each of fiscal years 2022 through 2026.
Except as provided in subparagraph (B), the cost of any facilitation activities carried out by the Secretary under subsection (e)(1) shall be collected-
If, at the end of the useful life of an eligible project or the termination of a capacity contract under subsection (f)(5), there is a remaining balance owed to the Treasury under this section, the balance shall be forgiven.
Funds expended to study projects that are considered pursuant to this section but that are not constructed shall be forgiven.
The Secretary may collect the costs of any activities carried out by the Secretary with respect to an eligible project in which the Secretary participates with an eligible entity under subsection (e)(1)(C) through rates charged to customers benefitting from the new transmission capability provided by the eligible project.
To facilitate eligible projects, the Secretary may-
The provision and receipt of assistance for an eligible project under paragraph (1) shall be subject to such terms and conditions as the Secretary determines to be appropriate-
In entering into capacity contracts under subsection (e)(1)(A), the Secretary shall seek to enter into capacity contracts that will encourage other entities to enter into contracts for the transmission capacity of the eligible project.
The amount paid by the Secretary to an eligible entity under a capacity contract for the right to the use of the transmission capacity of an eligible project shall be-
A capacity contract shall-
If the Secretary has not terminated a capacity contract under paragraph (5) before the applicable eligible project enters into service, the Secretary may enter into 1 or more contracts with a third party to market the transmission capacity of the eligible project to which the Secretary holds rights under the capacity contract.
Subject to subparagraph (D), the Secretary shall seek to ensure that any contract entered into under subparagraph (A) maximizes the financial return to the Federal Government.
The Secretary shall only select third parties for contracts under this paragraph through a competitive solicitation.
The marketing of capacity pursuant to this subsection, including any marketing by a third party under subparagraph (A), shall be undertaken consistent with the requirements of the Federal Power Act (16 U.S.C. 791a et seq.).
The Secretary shall seek to terminate a capacity contract as soon as practicable after determining that sufficient transmission capacity of the eligible project has been secured by other entities to ensure the long-term financial viability of the eligible project, including through 1 or more transfers under subparagraph (B).
On payment to the Secretary by a third party for transmission capacity to which the Secretary has rights under a capacity contract, the Secretary may transfer the rights to that transmission capacity to that third party.
On payment to the Secretary by the applicable eligible entity for transmission capacity to which the Secretary has rights under a capacity contract, the Secretary may relinquish the rights to that transmission capacity to the eligible entity.
A payment under subparagraph (B) or (C) shall be in an amount sufficient for the Secretary to recover any remaining costs incurred by the Secretary with respect to the quantity of transmission capacity affected by the transfer under subparagraph (B) or the relinquishment under subparagraph (C), as applicable.
The existence of a capacity contract does not preclude a Federal entity, including a Federal power marketing administration, from otherwise securing transmission capacity at any time from an eligible project, to the extent that the Federal entity is authorized to secure that transmission capacity.
Entering into a capacity contract under subsection (e)(1)(A) shall be considered a form of financial assistance described in section 1508.1(q)(1)(vii) of title 40, Code of Federal Regulations (as in effect on November 15, 2021).
Prior to entering into a capacity contract under this subsection, the Secretary shall consult with the relevant transmission planning region regarding the transmission planning region's identification of needs, and the Secretary shall minimize, to the extent possible, duplication or conflict with the transmission planning region's needs determination and selection of projects that meet such needs.
The rate of interest to be charged in connection with any loan made by the Secretary to an eligible entity under subsection (e)(1)(B) shall be fixed by the Secretary, taking into consideration market yields on outstanding marketable obligations of the United States of comparable maturities as of the date of the loan.
The Secretary may participate with an eligible entity with respect to an eligible project under subsection (e)(1)(C) if the Secretary determines that the eligible project-
Prior to taking action to facilitate an eligible project under subparagraph (A), (B), or (C) of subsection (e)(1), the Secretary shall certify that-
The Secretary may permit other entities to participate in the financing, construction, and ownership of eligible projects facilitated under this section.
Facilitation by the Secretary of an eligible project under this section does not create any obligation on the part of the Secretary to operate or maintain the eligible project.
For purposes of cost recovery under subsection (d)(4) and repayment of a loan issued under subsection (e)(1)(B), each eligible project facilitated by the Secretary under this section shall be treated as separate and distinct from-
Nothing in this section confers on the Secretary or any Federal power marketing administration any additional authority or obligation to provide ancillary services to users of transmission facilities constructed or upgraded under this section.
Nothing in this section affects-
Nothing in this section precludes an eligible project facilitated under this section from being eligible as a project under section 16421 of this title.
An eligible project may not be the subject of both-
In evaluating eligible projects for possible facilitation under this section, the Secretary shall prioritize projects that, to the maximum extent practicable-
42 U.S.C. § 18713
EDITORIAL NOTES
REFERENCES IN TEXTThe Federal Power Act, referred to in subsec. (f)(4)(D), is act June 10, 1920, ch. 285, 41 Stat. 1063, which is classified generally to chapter 12 (§791a et seq.) of Title 16, Conservation. For complete classification of this Act to the Code, see section 791a of Title 16 and Tables.
STATUTORY NOTES AND RELATED SUBSIDIARIES
WAGE RATE REQUIREMENTSFor provisions relating to rates of wages to be paid to laborers and mechanics on projects for construction, alteration, or repair work funded under div. D or an amendment by div. D of Pub. L. 117-58 including authority of Secretary of Labor, see section 18851 of this title.
- practices
- The term "practices" means design, financing, permitting, construction, commissioning, operation and maintenance, and other practices that contribute to achieving zero-net-energy buildings or facilities.
- project
- The terms "federally assisted housing" and "project" mean-(A) a public housing project (as such term is defined in section 3(b) of the United States Housing Act of 1937 [42 U.S.C. 1437a(b)] );(B) housing for which project-based assistance is provided under section 8 of the United States Housing Act of 1937 [42 U.S.C. 1437f] ;(C) housing that is assisted under section 1701q of title 12;(D) housing that is assisted under section 1701q of title 12, as such section existed before November 28, 1990;(E) housing financed by a loan or mortgage insured under section 1715l(d)(3) of title 12 that bears interest at a rate determined under the proviso of section 1715l(d)(5) of title 12;(F) housing insured, assisted, or held by the Secretary or a State or State agency under section 1715z-1 of title 12;(G) housing constructed or substantially rehabilitated pursuant to assistance provided under section 8(b)(2) of the United States Housing Act of 1937 [42 U.S.C. 1437f(b)(2)], as in effect before October 1, 1983, that is assisted under a contract for assistance under such section; and(H) housing that is assisted under section 8013 1 of this title.
- Secretary
- the term "Secretary" means- (A) the Secretary of Education for purposes of subtitle A (other than section 3201),(B) the Secretary of Agriculture for purposes of the amendments made by section 3201, and(C) the Secretary of Health and Human Services for purposes of subtitle B,