42 U.S.C. § 10365

Current through P.L. 118-106 (published on www.congress.gov on 10/04/2024)
Section 10365 - Hydroelectric power assessment
(a) Duty of Secretary of Energy

The Secretary of Energy, in consultation with the Administrator of each Federal Power Marketing Administration, shall assess each effect of, and risk resulting from, global climate change with respect to water supplies that are required for the generation of hydroelectric power at each Federal water project that is applicable to a Federal Power Marketing Administration.

(b) Access to appropriate data
(1) In general

In carrying out each assessment under subsection (a), the Secretary of Energy shall consult with the United States Geological Survey, the National Oceanic and Atmospheric Administration, the program, and each appropriate State water resource agency, to ensure that the Secretary of Energy has access to the best available scientific information with respect to presently observed impacts and projected future impacts of global climate change on water supplies that are used to produce hydroelectric power.

(2) Access to data for certain assessments

In carrying out each assessment under subsection (a), with respect to the Bonneville Power Administration and the Western Area Power Administration, the Secretary of Energy shall consult with the Commissioner to access data and other information that-

(A) is collected by the Commissioner; and
(B) the Secretary of Energy determines to be necessary for the conduct of the assessment.
(c) Report

Not later than 2 years after March 30, 2009, and every 5 years thereafter, the Secretary of Energy shall submit to the appropriate committees of Congress a report that describes-

(1) each effect of, and risk resulting from, global climate change with respect to-
(A) water supplies used for hydroelectric power generation; and
(B) power supplies marketed by each Federal Power Marketing Administration, pursuant to-
(i) long-term power contracts;
(ii) contingent capacity contracts; and
(iii) short-term sales; and
(2) each recommendation of the Administrator of each Federal Power Marketing Administration relating to any change in any operation or contracting practice of each Federal Power Marketing Administration to address each effect and risk described in paragraph (1), including the use of purchased power to meet long-term commitments of each Federal Power Marketing Administration.
(d) Authority

The Secretary of Energy may enter into contracts, grants, or other agreements with appropriate entities to carry out this section.

(e) Costs
(1) Nonreimbursable

Any costs incurred by the Secretary of Energy in carrying out this section shall be nonreimbursable.

(2) PMA costs

Each Federal Power Marketing Administration shall incur costs in carrying out this section only to the extent that appropriated funds are provided by the Secretary of Energy for that purpose.

(f) Authorization of appropriations

There are authorized to be appropriated such sums as are necessary to carry out this section for each of fiscal years 2009 through 2023, to remain available until expended.

42 U.S.C. § 10365

Pub. L. 111-11, title IX, §95059505,, 123 Stat. 1336.
Administrator
The term "Administrator" means the Administrator of the National Oceanic and Atmospheric Administration.
Commissioner
The term "Commissioner" means the Commissioner of Reclamation.
Federal Power Marketing Administration
The term "Federal Power Marketing Administration" means-(A) the Bonneville Power Administration;(B) the Southeastern Power Administration;(C) the Southwestern Power Administration; and(D) the Western Area Power Administration.
Secretary
The term "Secretary" means the Secretary of Housing and Urban Development.1See References in Text note below.
program
The term "program" means the regional integrated sciences and assessments program-(A) established by the Administrator; and(B) that is comprised of 8 regional programs that use advances in integrated climate sciences to assist decisionmaking processes.
project
The terms "federally assisted housing" and "project" mean-(A) a public housing project (as such term is defined in section 3(b) of the United States Housing Act of 1937 [42 U.S.C. 1437a(b)] );(B) housing for which project-based assistance is provided under section 8 of the United States Housing Act of 1937 [42 U.S.C. 1437f] ;(C) housing that is assisted under section 1701q of title 12;(D) housing that is assisted under section 1701q of title 12, as such section existed before November 28, 1990;(E) housing financed by a loan or mortgage insured under section 1715l(d)(3) of title 12 that bears interest at a rate determined under the proviso of section 1715l(d)(5) of title 12;(F) housing insured, assisted, or held by the Secretary or a State or State agency under section 1715z-1 of title 12;(G) housing constructed or substantially rehabilitated pursuant to assistance provided under section 8(b)(2) of the United States Housing Act of 1937 [42 U.S.C. 1437f(b)(2)], as in effect before October 1, 1983, that is assisted under a contract for assistance under such section; and(H) housing that is assisted under section 80131 of this title.