Section 4702 - Prohibition on release of contractor proposals
(a) DEFINITION.-In this section, the term "proposal" means a proposal, including a technical, management, or cost proposal, submitted by a contractor in response to the requirements of a solicitation for a competitive proposal.
(b) PROHIBITION.-A proposal in the possession or control of an executive agency may not be made available to any person under section 552 of title 5.
(c) NONAPPLICATION.-Subsection (b) does not apply to a proposal that is set forth or incorporated by reference in a contract entered into between the agency and the contractor that submitted the proposal.

41 U.S.C. § 4702

Pub. L. 111-350, §3, Jan. 4, 2011, 124 Stat. 3794.

HISTORICAL AND REVISION NOTE
Revised SectionSource (U.S. Code)Source (Statutes at Large)
4702(a)41:253b(m)(3).June 30, 1949, ch. 288, title III, §303B(m), as added Pub. L. 104-201, §821, 110 Stat. 2609.
4702(b)41:253b(m)(1).
4702(c)41:253b(m)(2).
In subsection (b), the words "Except as provided in paragraph (2)" are omitted as unnecessary.