The completion of a post-authorization change report prepared by the Corps of Engineers for a water resources development project-
With respect to a post-authorization change report subject to review by the Secretary, the Secretary shall, not later than 120 days after the date of completion of such report-
Not later than 120 days after December 16, 2016, with respect to any post-authorization change report that was completed prior to December 16, 2016, and is subject to a review by the Secretary that has yet to be completed, the Secretary shall complete review of, and provide recommendations to Congress with respect to, the report.
In this section, the term "post-authorization change report" includes-
33 U.S.C. § 2282e
EDITORIAL NOTES
CODIFICATIONSection was enacted as part of the Water Resources Development Act of 2016, and also as part of the Water Infrastructure Improvements for the Nation Act, also known as the WIIN Act, and not as part of the Water Resources Development Act of 1986 which comprises this chapter.
STATUTORY NOTES AND RELATED SUBSIDIARIES
"SECRETARY" DEFINED Secretary means the Secretary of the Army, see section 1002 of Pub. L. 114-322 set out as a note under section 2201 of this title.