Current with legislation from the 2023 Regular and Special Sessions signed by the Governor as of November 21, 2023.
Section 53.103 - Lien On Reserved Funds A claimant has a lien on the reserved funds if the claimant:
(1) sends the notices required by this chapter in the time and manner required; and (2) except as allowed by Section 53.057(f), files an affidavit claiming a lien not later than the 30th day after the earliest of the date: (A) the work is completed; (B) the original contract is terminated; or (C) the original contractor abandons performance under the original contract.Amended by Acts 2021, Texas Acts of the 87th Leg. - Regular Session, ch. 690,Sec. 18, eff. 1/1/2022.Amended By Acts 2011, 82nd Leg., R.S., Ch. 499, Sec. 3, eff. 9/1/2011.Amended By Acts 2005, 79th Leg., Ch. 1003, Sec. 1, eff. 9/1/2005. Acts 1983, 68th Leg., p. 3545, ch. 576, Sec. 1, eff. 1/1/1984.