Current through the 2024 Regular Session
Section 77.55.400 - Determination as to whether construction is a hydraulic project-Preapplication determination-Review and comment period-Written determination(1) A person proposing construction or other work landward of the ordinary high water line that will use, divert, obstruct, or change the natural flow or bed of state waters shall submit a permit application to the department. However, if a person is unsure about whether the work requires a permit, they may request a preapplication determination from the department. The department must evaluate the proposed work and determine if the work is a hydraulic project and, if so, whether a permit from the department is required to ensure adequate protection of fish life.(2) The preapplication determination request must be submitted through the department's online permitting system and must contain:(a) A description of the proposed project;(b) A map showing the location of the project site; and(c) Preliminary plans and specifications of the proposed construction or work, if available.(3) The department shall provide tribes and local governments a seven calendar day review and comment period. The department shall consider all applicable written comments received before issuing a determination.(4) The department shall issue a written determination, including the rationale for the decision, within twenty-one calendar days of receiving the request.(5) Determinations made according to the provisions of this section are not subject to the requirements of chapter 43.21C RCW.Added by 2019 c 290,§ 4, eff. 7/28/2019.Finding-Intent- 2019 c 290 : See note following RCW 77.12.085.