Wash. Rev. Code § 70.108.160

Current through the 2024 Regular Session
Section 70.108.160 - Preparations-Completion requirements

All preparations required to be made by the provisions of this chapter on the music festival site shall be completed thirty days prior to the first day scheduled for the festival. Upon such date or such earlier date when all preparations have been completed, the promoter shall notify the issuing authority thereof, and the issuing authority shall make an inspection of the festival site to determine if such preparations are in reasonably full compliance with plans submitted pursuant to RCW 70.108.040. If a material violation exists the issuing authority shall move to revoke the music festival permit in the manner provided by RCW 70.108.080.

RCW 70.108.160

1972 ex.s. c 123 § 6.