Wash. Rev. Code § 47.01.417

Current through 2024
Section 47.01.417 - State route No. 520 improvements-Finance plan-Revenue sources and savings recognition

The state route number 520 bridge replacement and HOV project finance plan must include:

(1) Recognition of revenue sources that include: One billion seven hundred million dollars in state and federal funds allocated to the project; one billion five hundred million dollars to two billion dollars in tolling revenue, including early tolls that could begin in late 2009; eighty-five million dollars in federal urban partnership grant funds; and other contributions from private and other government sources; and
(2) Recognition of savings to be realized from:
(a) Potential early construction of traffic improvements from the eastern Lake Washington shoreline to 108th Avenue Northeast in Bellevue;
(b) Early construction of a single string of pontoons to support two lanes that are for transit and high occupancy vehicle travel and four general purpose lanes;
(c) Preconstruction tolling to reduce total financing costs; and
(d) A deferral of the sales taxes paid on construction costs.

RCW 47.01.417

2008 c 270 § 3.

Finding-2008 c 270: See note following RCW 47.01.408.