Current through the 2024 Regular Session
Section 36.70B.110 - Notice of application-Required elements-Integration with other review procedures-Administrative appeals(1) Not later than April 1, 1996, a local government planning under RCW 36.70A.040 shall provide a notice of application to the public and the departments and agencies with jurisdiction as provided in this section. If a local government has made a threshold determination under chapter 43.21C RCW concurrently with the notice of application, the notice of application may be combined with the threshold determination and the scoping notice for a determination of significance. Nothing in this section prevents a determination of significance and scoping notice from being issued prior to the notice of application. Nothing in this section or this chapter prevents a lead agency, when it is a project proponent or is funding a project, from conducting its review under chapter 43.21C RCW or from allowing appeals of procedural determinations prior to submitting a project permit.(2) The notice of application shall be provided within 14 days after the determination of completeness as provided in RCW 36.70B.070 and, except as limited by the provisions of subsection (4)(b) of this section, must include the following in whatever sequence or format the local government deems appropriate: (a) The date of application, the date of the notice of completion for the application, and the date of the notice of application;(b) A description of the proposed project action and a list of the project permits included in the application and, if applicable, a list of any studies requested under RCW 36.70B.070;(c) The identification of other permits not included in the application to the extent known by the local government;(d) The identification of existing environmental documents that evaluate the proposed project, and, if not otherwise stated on the document providing the notice of application, such as a city land use bulletin, the location where the application and any studies can be reviewed;(e) A statement of the public comment period, which shall be not less than fourteen nor more than thirty days following the date of notice of application, and statements of the right of any person to comment on the application, receive notice of and participate in any hearings, request a copy of the decision once made, and any appeal rights. A local government may accept public comments at any time prior to the closing of the record of an open record predecision hearing, if any, or, if no open record predecision hearing is provided, prior to the decision on the project permit;(f) The date, time, place, and type of hearing, if applicable and scheduled at the date of notice of the application;(g) A statement of the preliminary determination, if one has been made at the time of notice, of those development regulations that will be used for project mitigation and of consistency as provided in RCW 36.70B.030(2) and 36.70B.040; and(h) Any other information determined appropriate by the local government.(3) If an open record predecision hearing is required for the requested project permits, the notice of application shall be provided at least fifteen days prior to the open record hearing.(4) A local government shall use reasonable methods to give the notice of application to the public and agencies with jurisdiction and may use its existing notice procedures. A local government may use different types of notice for different categories of project permits or types of project actions. If a local government by resolution or ordinance does not specify its method of public notice, the local government shall use the methods provided for in (a) and (b) of this subsection. Examples of reasonable methods to inform the public are:(a) Posting the property for site-specific proposals;(b) Publishing notice, including at least the project location, description, type of permit(s) required, comment period dates, and location where the notice of application required by subsection (2) of this section and the complete application may be reviewed, in the newspaper of general circulation in the general area where the proposal is located or in a local land use newsletter published by the local government;(c) Notifying public or private groups with known interest in a certain proposal or in the type of proposal being considered;(d) Notifying the news media;(e) Placing notices in appropriate regional or neighborhood newspapers or trade journals;(f) Publishing notice in agency newsletters or sending notice to agency mailing lists, either general lists or lists for specific proposals or subject areas; and(g) Mailing to neighboring property owners.(5) A notice of application shall not be required for project permits that are categorically exempt under chapter 43.21C RCW, unless an open record predecision hearing is required or an open record appeal hearing is allowed on the project permit decision.(6) A local government shall integrate the permit procedures in this section with environmental review under chapter 43.21C RCW as follows:(a) Except for a threshold determination and except as otherwise expressly allowed in this section, the local government may not issue a decision or a recommendation on a project permit until the expiration of the public comment period on the notice of application.(b) If an open record predecision hearing is required, the local government shall issue its threshold determination at least fifteen days prior to the open record predecision hearing.(c) Comments shall be as specific as possible.(d) A local government is not required to provide for administrative appeals of its threshold determination. If provided, an administrative appeal must be filed within fourteen days after notice that the determination has been made and is appealable. Except as otherwise expressly provided in this section, the appeal hearing on a threshold determination must be consolidated with any open record hearing on the project permit.(7) At the request of the applicant, a local government may combine any hearing on a project permit with any hearing that may be held by another local, state, regional, federal, or other agency, if: (a) The hearing is held within the geographic boundary of the local government; and(b) The applicant agrees to the schedule in the event that additional time is needed in order to combine the hearings. All agencies of the state of Washington, including municipal corporations and counties participating in a combined hearing, are hereby authorized to issue joint hearing notices and develop a joint format, select a mutually acceptable hearing body or officer, and take such other actions as may be necessary to hold joint hearings consistent with each of their respective statutory obligations.(8) All state and local agencies shall cooperate to the fullest extent possible with the local government in holding a joint hearing if requested to do so, as long as:(a) The agency is not expressly prohibited by statute from doing so;(b) Sufficient notice of the hearing is given to meet each of the agencies' adopted notice requirements as set forth in statute, ordinance, or rule; and(c) The agency has received the necessary information about the proposed project from the applicant to hold its hearing at the same time as the local government hearing.(9) A local government is not required to provide for administrative appeals. If provided, an administrative appeal of the project decision and of any environmental determination issued at the same time as the project decision, shall be filed within fourteen days after the notice of the decision or after other notice that the decision has been made and is appealable. The local government shall extend the appeal period for an additional seven days, if state or local rules adopted pursuant to chapter 43.21C RCW allow public comment on a determination of nonsignificance issued as part of the appealable project permit decision.(10) The applicant for a project permit is deemed to be a participant in any comment period, open record hearing, or closed record appeal.(11) Each local government planning under RCW 36.70A.040 shall adopt procedures for administrative interpretation of its development regulations.Reenacted and amended by 2023 c 338,§ 10, eff. 7/23/2023.1997 c 396 § 1; 1995 c 347 § 415.Severability-1997 c 429: See note following RCW 36.70A.3201.