Each electric utility must develop a plan consistent with this section.
RCW 19.280.030
Findings-Intent-Effective date- 2024 c 351 : See notes following RCW 80.86.010.
Finding-Intent- 2023 c 229 : "(1) The legislature finds that the electric power system serving Washington will require additional high voltage transmission capacity to achieve the state's objectives and legal requirements. Washington must reduce its greenhouse gas emissions under state law, and the 2021 state energy strategy finds that this will require a significant increase in the use of renewable or nonemitting electricity in place of fossil fuels now used in the transportation, industry, and building sectors.
(2) The legislature anticipated the crucial role of additional transmission capacity in 2019 in the enactment of the clean energy transformation act and directed the energy facilities site evaluation council to convene a transmission corridors work group. The transmission corridors work group issued its final report on October 31, 2022, in which it confirmed the central role of transmission and recommended actions to achieve the expansion of transmission capacity to address this need.
(3) Expanded transmission capacity and the more effective use of existing transmission capacity will provide benefits to electricity consumers in the state by enhancing the reliability of the electric power system and increasing access to more affordable sources of electricity within the state and across the western United States and Canada.
(4) Existing constraints on transmission capacity within the state already present challenges in ensuring adequate and affordable supplies of clean electricity. Of particular concern is the capability of the transmission system to deliver clean electricity into and within the central Puget Sound area.
(5) There are multiple issues that contribute to the challenge of making timely and cost-effective expansions of the high voltage transmission system. Among those challenges is the need for a more proactive transmission planning process using a longer planning period than current law requires. Transmission planning must reflect not just the requirements to connect individual generating resources to the grid but also the need to transfer electricity across the state and the west. Transmission planning must incorporate state policies and laws in planning objectives.
(6) Certain transmission projects are of significant state interest due to their impact on the access of multiple utilities and communities to gain access to clean, affordable electricity supplies and obtain electricity that is necessary to comply with state laws.
(7) The legislature intends and affirms that the option to use local government permitting processes remains available for transmission projects not subject to mandatory jurisdiction under RCW 80.50.060(2).
(8) Transmission projects typically take at least a decade to develop and permit. This timing presents particular challenges for achieving the state's greenhouse gas emissions reduction mandates, which include ambitious benchmarks as early as 2030. There is a need to accelerate the timeline for transmission development while still protecting other Washington values.
(9) Some electric utilities rely entirely or primarily on a contracted network transmission provider for required transmission services. These electric utilities may contribute to the objectives of this act by requesting that each provider of network transmission service to the utilities include the provisions of chapter 288, Laws of 2019 and chapter 70A.45 RCW as public policy mandates in the transmission service provider's transmission planning process." [2023 c 229 s 1.]
Intent- 2021 c 300 : See note following RCW 47.01.520.
Findings-Intent-Effective date- 2019 c 288 : See RCW 19.405.010 and 19.405.901.
Finding-Intent-2015 3rd sp.s. c 19: See note following RCW 39.35.010.
Findings-Purpose- 2011 c 180 : See note following RCW 80.80.010.