Ohio Rev. Code § 4926.54

Current with legislation from 2024 received as of August 15, 2024.
Section 4926.54 - Rebuttable presumptions

In a complaint filed under section 4926.39 of the Revised Code, there is a rebuttable presumption that each of the following is just and reasonable:

(A) The time frame to grant or deny access, if it is within the time frame established by the federal communications commission;
(B) The process for make-ready work, if it is in accordance with the process for make-ready work under 47 U.S.C. 224 and the federal communications commission orders and regulations implementing that section;
(C) The charged rate, if the electric cooperative can show that its charged rate does not exceed an annual recurring attachment rate calculated in accordance with the cable pole attachment rate formula in 47 U.S.C. 224(d) and federal communications commission orders and regulations implementing that formula.

R.C. § 4926.54

Added by 134th General Assembly, HB 2,§1, eff. 5/17/2021.