The estimate of the total decommissioning costs of a utility facility, as described in division (B)(3) of section 4906.211 of the Revised Code, shall be recalculated every five years by an engineer retained by the applicant.
R.C. § 4906.212
The estimate of the total decommissioning costs of a utility facility, as described in division (B)(3) of section 4906.211 of the Revised Code, shall be recalculated every five years by an engineer retained by the applicant.