Ohio Rev. Code § 3318.41

Current with legislation from 2024 received as of August 15, 2024.
Section 3318.41 - Annual assessment of needs
(A)
(1) The Ohio facilities construction commission annually shall assess the classroom facilities needs of the number of joint vocational school districts that the commission reasonably expects to be able to provide assistance to in a fiscal year, based on the amount set aside for that fiscal year under division (B) of section 3318.40 of the Revised Code and the order of priority prescribed in division (B) of section 3318.42 of the Revised Code, except that in fiscal year 2004 the commission shall conduct at least the five assessments prescribed in division (E) of section 3318.40 of the Revised Code.

Upon conducting an assessment of the classroom facilities needs of a school district, the commission shall make a determination of all of the following:

(a) The number of classroom facilities to be included in a project and the basic project cost of acquiring the classroom facilities included in the project. The number of facilities and basic project cost shall be determined in accordance with the specifications adopted under section 3318.311 of the Revised Code except to the extent that compliance with such specifications is waived by the commission pursuant to the rule of the commission adopted under division (F) of section 3318.40 of the Revised Code.
(b) The school district's portion of the basic project cost as determined under division (C) of section 3318.42 of the Revised Code;
(c) The remaining portion of the basic project cost that shall be supplied by the state;
(d) The amount of the state's portion of the basic project cost to be encumbered in accordance with section 3318.11 of the Revised Code in the current and subsequent fiscal years from funds set aside under division (B) of section 3318.40 of the Revised Code.
(2) Divisions (A), (C), and (D) of section 3318.03 of the Revised Code apply to any project under sections 3318.40 to 3318.45 of the Revised Code.
(B)
(1) If the commission makes a determination under division (A) of this section in favor of the acquisition of classroom facilities for a project under sections 3318.40 to 3318.45 of the Revised Code, such project shall be conditionally approved. Such conditional approval shall be submitted to the controlling board for approval. The controlling board shall immediately approve or reject the commission's determination, conditional approval, the amount of the state's portion of the basic project cost, and the amount of the state's portion of the basic project cost to be encumbered in the current fiscal year. In the event of approval by the controlling board, the commission shall certify the conditional approval to the joint vocational school district board of education and shall encumber the approved funds for the current fiscal year.
(2) No school district that receives assistance under sections 3318.40 to 3318.45 of the Revised Code shall have another such project conditionally approved until the expiration of twenty years after the school district's prior project was conditionally approved, unless the school district board demonstrates to the satisfaction of the commission that the school district has experienced since conditional approval of its prior project an exceptional increase in enrollment or program requirements significantly above the school district's design capacity under that prior project as determined by rule of the commission. Any rule adopted by the commission to implement this division shall be tailored to address the classroom facilities needs of joint vocational school districts.
(C) In addition to generating the amount of the school district's portion of the basic project cost as determined under division (C) of section 3318.42 of the Revised Code, in order for a school district to receive assistance under sections 3318.40 to 3318.45 of the Revised Code, the school district board shall set aside school district moneys for the maintenance of the classroom facilities included in the school district's project in the amount and manner prescribed in section 3318.43 of the Revised Code.
(D)
(1) The conditional approval for a project certified under division (B)(1) of this section shall lapse and the amount reserved and encumbered for such project shall be released unless both of the following conditions are satisfied:
(a) Within one hundred twenty days following the date of certification of the conditional approval to the joint vocational school district board, the school district board accepts the conditional approval and certifies to the commission the school district board's plan to generate the school district's portion of the basic project cost, as determined under division (C) of section 3318.42 of the Revised Code, and to set aside moneys for maintenance of the classroom facilities acquired under the project, as prescribed in section 3318.43 of the Revised Code.
(b) Within sixteen months following the date of certification of the conditional approval to the school district board, the electors of the school district vote favorably on any ballot measures proposed by the school district board to generate the school district's portion of the basic project cost.

For purposes of this section, "conditional approval" includes any conditional approval made by the Ohio facilities commission and approved by the controlling board in calendar year 2023.

(2) If the school district board or electors fail to satisfy the conditions prescribed in division (D)(1) of this section and the amount reserved and encumbered for the school district's project is released, the school district shall be given first priority over other joint vocational school districts for project funding under sections 3318.40 to 3318.45 of the Revised Code as such funds become available, subject to section 3318.054 of the Revised Code.
(E) If the conditions prescribed in division (D)(1) of this section are satisfied, the commission and the school district board shall enter into an agreement as prescribed in section 3318.08 of the Revised Code and shall proceed with the development of plans, cost estimates, designs, drawings, and specifications as prescribed in section 3318.091 of the Revised Code.
(F) Costs in excess of those approved by the commission under section 3318.091 of the Revised Code shall be payable only as provided in sections 3318.042 and 3318.083 of the Revised Code.
(G) Advertisement for bids and the award of contracts for construction of any project under sections 3318.40 to 3318.45 of the Revised Code shall be conducted in accordance with section 3318.10 of the Revised Code.
(H) In accordance with division (R) of section 3318.08 of the Revised Code, the state funds reserved and encumbered and the funds provided by the school district to pay the basic project cost of a project under sections 3318.40 to 3318.45 of the Revised Code shall be spent simultaneously in proportion to the state's and the school district's respective portions of that basic project cost.
(I) Sections 3318.13, 3318.14, and 3318.16 of the Revised Code apply to projects under sections 3318.40 to 3318.45 of the Revised Code.

R.C. § 3318.41

Amended by 135th General Assembly, HB 101,§101.01, eff. 4/30/2024.
Amended by 135th General Assembly, HB 33,§101.01, eff. 10/3/2023.
Amended by 132nd General Assembly, HB 49,§101.01, eff. 9/29/2017.
Amended by 129th General Assembly, HB 153, §101.01. See act for effective dates.
Effective Date: 09-26-2003; 05-06-2005