N.D. Cent. Code § 61-35-54

Current through 2024 Legislative Session
Section 61-35-54 - Engineer's report required - Contents

After a special improvement district has been created, the board, if it deems it necessary to make any of the improvements set out in section 61-35-48 in the manner provided in this chapter, shall direct the engineer for the district, or some other competent engineer, to prepare a report as to the general nature, purpose, and feasibility of the proposed improvement. The engineer shall prepare profiles, plans, and specifications of the proposed project and estimates of the total cost. The estimate of costs prepared by the engineer must include acquisition of right of way and must be in sufficient detail to allow the board to determine the probable share of the total costs that will be assessed against each of the affected landowners in the proposed assessment district.

N.D.C.C. § 61-35-54