N.M. Stat. § 15-3B-11

Current through 2024, ch. 69
Section 15-3B-11 - Capital projects; contingency limitation

No more than six and one-half percent of the cost of a capital project shall be used for contingencies. For the purposes of this section, "contingencies" means unforeseeable elements of cost within the defined scope of the capital project.

NMS § 15-3B-11

1978 Comp., § 15-3-23.2, enacted by Laws 1984 (1st S.S.), ch. 10, § 10; recompiled and amended as 1978 Comp., § 15-3B-11 by Laws 2001, ch. 319, § 11.