Section 58:10A-24 - Permit for modificationAn owner or operator of a facility proposing to replace, install, expand or substantially modify the facility shall obtain a permit therefor from the commissioner. The commissioner shall not issue a permit unless the owner or operator demonstrates that:
a. The facility is constructed of materials that meet or exceed the standards contained in, and is installed in a manner consistent with, the State Uniform Construction Code adopted pursuant to the "State Uniform Construction Code Act," P.L. 1975, c. 217 (C. 52:27D-119 et seq.) and with the rules and regulations adopted pursuant to this act;b. The facility is equipped with either an approved method of secondary containment or a monitoring system;c. The facility utilizes corrosion control features necessary to protect the structural integrity of underground storage tanks susceptible to corrosion.L.1986, c.102, s.4, eff. 9/3/1986.