The extension granted pursuant to this section shall be for a period that is two years beyond what otherwise would be the deadline for the qualified solar electric power generation facility to achieve commercial operation pursuant to the applicable board order granting conditional certification as connected to the distribution system, including any extensions previously authorized by law, rule, regulation, or applicable board order. The automatic extension shall protect the qualified solar electric power generation facility from forfeiting the following:
The order shall be issued by the board on a non-discretionary basis, and no factual investigation or hearing by the board shall be conducted. The order shall acknowledge receipt of certification of the tolling event, extend the previously established project completion or commercial operation deadline date for the facility by an amount of time prescribed by this section, and provide such other and further relief as the board may deem appropriate.
In the event a qualified solar electric power generation facility receiving an extension pursuant to this section achieves commercial operation between 12 and 24 months beyond what otherwise would be the deadline for the qualified solar electric power generation facility to achieve commercial operation pursuant to the applicable board order granting conditional certification as connected to the distribution system, including any extensions previously authorized by law, rule, regulation, or applicable board order, that qualified solar electric power generation facility shall receive the solar incentive pursuant to the solar incentive program for which application was made at a discount of 15 percent of the original incentive value.
"Project sponsor" means a municipality, business entity, person, property owner, developer, redeveloper, or other interest that is the party pursuing the development and implementation of a qualified solar electric power generation facility under a solar incentive program administered by the board.
"Qualified solar electric power generation facility" or "facility" means a solar electric power generation facility that has, as of the effective date of P.L.2023, c.158 (C.48:3-121), received by board order conditional certification to participate in a solar incentive program pursuant to subsection t. of section 38 of P.L.1999, c.23 (C.48:3-87).
"Tolling event" means any action or inaction of the PJM Interconnection, L.L.C., any moratorium in new applications declared by the PJM Interconnection, L.L.C., any deferral in processing of existing applications by the PJM Interconnection, L.L.C., any new application process, study, report, or analysis established by the PJM Interconnection, L.L.C., to approve and contract a project, the deferral to negotiate, execute, and deliver any other engineering or other studies, agreements, or approvals required by the PJM Interconnection, L.L.C., as a prerequisite to project interconnection or commercial operation of a qualified solar electric power generation facility.
N.J.S. § 48:3-121