Section 90-4-1221 - Requirements prior to project constructionPrior to starting construction under this part, the governmental body shall enter into a contract or contracts:
(1) with a transmission services provider to interconnect with the transmission or distribution facilities of a utility or cooperative;(2) that ensure that all ancillary services as required by the control area operator are available to regulate the generation of electricity from the project;(3) for the sale of electricity from the project; and(4) with a tribal government for projects being constructed within the exterior boundaries of that tribal government's Indian reservation.En. Sec. 16, Ch. 378, L. 2007.