Section 85-15-210 - Preparation and approval of plans(1) A person may not begin construction of a high-hazard dam as determined under 85-15-209 without first obtaining a construction permit from the department.(2) An application for a construction permit must be submitted to the department and must contain: (a) plans and specifications for the proposed construction, prepared by or under the direction of an engineer experienced in dam design and construction; and(b) other data and information required by the department.(3) Within 60 calendar days after receipt of the application and any additional information requested by the department, the department shall: (a) issue a construction permit or deny the application, as filed; or(b) issue a construction permit upon terms, conditions, or modifications the department considers appropriate.En. Sec. 7, Ch. 501, L. 1985.