Current through the 2023 Regular Session
Section 75-20-208 - Certain electric transmission lines - verification of requirements(1) Prior to constructing a transmission line under 75-20-104(10)(a)(ii), the person planning to construct the line shall provide to the department within 36 months of the date of the public notice provided under 75-20-207, unless extended by the department for good cause: (a) copies of the right-of-way agreements or options for a right-of-way containing sufficient information to establish landowner consent to construct the line; and(b) sufficient information for the department to verify that the requirements of 75-20-104(10)(a)(ii) are satisfied.(2) The provisions of 75-20-104(10)(a)(ii) do not apply to any facility for which public notice under 75-20-207 has been given but for which the requirements of subsection (1) of this section have not been complied with.Amended by Laws 2021, Ch. 13,Sec. 8, eff. 10/1/2021.Amended by Laws 2019, Ch. 447,Sec. 4, eff. 5/10/2019.En. Sec. 3, Ch. 597, L. 1987; amd. Sec. 216, Ch. 418, L. 1995; amd. Sec. 537, Ch. 546, L. 1995; amd. Sec. 8, Ch. 329, L. 1997; amd. Sec. 4, Ch. 293, L. 2001.