Current through Public Act 171 of the 2024 Legislative Session
Section 324.11511 - Construction permit; approval or denial of issuance; expiration; renewal; fee(1) The department shall notify the clerk of the municipality in which the disposal area is proposed to be located and the applicant of its approval or denial of an application for a construction permit under section 11509 within 10 days after the final decision is made.(2) A construction permit expires 1 year after the date of issuance, unless development under the construction permit is initiated within that year. A construction permit that has expired may be renewed upon payment of a permit renewal fee of $500.00 and submission of any additional relevant information the department may require.Amended by 2022, Act 245,s 3, eff. 3/29/2023.Amended by 2011, Act 215,s 1, eff. 11/10/2011.Amended by 2004, Act 325, s 17, eff. 9/10/2004.1994, Act 451, Eff. 3/30/1995 ;--Am. 1996, Act 358, Eff. 10/1/1996.