Me. Stat. tit. 38 § 490-M

Current through 131st (2023-2024) Legislature Chapter 684
Section 490-M - Erosion control requirements for clay, topsoil, or silt excavations of less than 5 acres

An excavation of less than 5 acres of land for clay, topsoil or silt must be conducted and reclaimed in accordance with the following standards. [1995, c. 700, §34(NEW).]

1.Stabilization and control. Sediment may not leave the parcel or enter a protected natural resource as defined in section 480-B. Properly installed erosion control measures must be in place before the excavation begins. Vegetative cover must be established on all affected land. Topsoil must be placed, seeded and mulched within 7 days of final grading. Permanent vegetative cover is acceptable for purposes of erosion control if, within one growing season of seeding, the planting of trees and shrubs results in a permanent stand or a stand capable of regeneration and succession sufficient to ensure a 75% survival rate and the planting of all materials in permanent 90% ground coverage.

[1995, c. 700, §34(NEW).]

2.Phases. The excavation must be reclaimed in phases so that the working pit does not exceed 2 acres at any one time.

[1995, c. 700, §34(NEW).]

38 M.R.S. § 490-M

1995, c. 700, § 34 (NEW) .