A person may not construct, cause to be constructed or operate a solar energy development with ground-mounted solar panels occupying 3 or more acres without first obtaining approval of a decommissioning plan from the environmental permitting entity under section 3495. [2021, c. 151, §1(NEW).]
35-A M.R.S. § 3492