P.R. Laws tit. 29, § 202

2019-02-20 00:00:00+00
§ 202. Subcontracts

When the contractor of a work under construction subcontracts any part or labor to be performed therein, he shall file with the Secretary of Labor and Human Resources a copy of the subcontract executed with the subcontractor not later than ten (10) days after its execution. The contractor shall have this same duty if the subcontractor, in his turn, contracts with a second subcontractor for any part or labor of the work under construction.

History —June 22, 1961, No. 111, p. 223, § 11, eff. 90 days after June 22, 1961.