Ind. Code § 5-16-5.5-5

Current through P.L. 171-2024
Section 5-16-5.5-5 - Payment of subcontractor; certification of receipt

Within ten (10) days of the receipt of any payment by the state agency or escrow agent, the contractor or escrow agent shall pay all subcontractors with whom he has contracted their share of the payment the contractor received based upon the service performed by the subcontractor. The contractor shall furnish upon request a sworn statement or certification at the time of payment to him that the subcontractor has received his share of the previous payment to the contractor. The making of an incorrect certification may be considered a breach of contract by the state agency, and it may exercise all of its prerogatives set out in the contract in addition to the remedies for falsifying an affidavit. Such an action may also result in a suspension of prequalification with the certification board established under IC 4-13.6-3-3.

IC 5-16-5.5-5

(Formerly: Acts1972 , P.L. 44, SEC.1.) As amended by P.L. 33-1983, SEC.16; P.L. 24-1985, SEC.15.