Ind. Code § 5-16-13-9

Current through P.L. 171-2024
Section 5-16-13-9 - Tier 1 contractor required work, materials, or services contribution to public works contract

Each tier 1 contractor must contribute in:

(1) work performed by the tier 1 contractor's employees;
(2) materials supplied directly by the tier 1 contractor;
(3) services supplied directly by the tier 1 contractor's employees; or
(4) any combination of subdivisions (1) through (3);

at least fifteen percent (15%) of the tier 1 contractor's total contract price as determined at the time the contract is awarded.

IC 5-16-13-9

Added by P.L. 252-2015, SEC. 12, eff. 7/1/2015.