Current through P.L. 171-2024
Section 36-9-36-24 - Contracts; scope; actions to enjoin performance(a) The contract for an improvement must be for the entire improvement.(b) After the execution of a contract for an improvement, the validity of the contract may be questioned only in an action to enjoin the performance of the contract. This action must be brought: (1) before the actual commencement of work under the contract, for an improvement by a county; or(2) before the later of the following, for an improvement by a municipality: (A) The actual commencement of work under the contract.(B) Not later than ten (10) days after the execution of the contract.As added by P.L. 98-1993, SEC.7.