the county surveyor shall include in the plans the grade and cross section requirements for a new crossing, or the requirements for altering, enlarging, repairing, or replacing the crossing. The surveyor shall mail a copy of the requirements addressed to the owner of the highway or right-of-way.
the cost of the work on the crossing shall be paid by the owner of the public highway. This cost may not be considered by the county surveyor or by the board in determining the cost of the work on the drain or in assessing benefits and damages. However, if it is necessary for the owner of a public highway to construct a new crossing because of a cut-off for the purpose of shortening or straightening a regulated drain, the owner of the public highway shall pay one-half (1/2) of the cost of the new crossing, and the remainder shall be included in the cost of the work on the drain.
shall pay one-half (1/2) of the cost of the work on the crossing and the remainder shall be included in the cost of the work on the drain.
IC 36-9-27-71
Pre-Local Government Recodification Citation: 19-4-6-5.