For industrial permits, other than coal mine permits or stone quarry permits, the annual base fee per facility is:
plus the following annual discharge flow fee per facility:
Daily Average Actual Flow in MGD | Fee | |
.001 - | .05 | $240 |
.051 - | .1 | $360 |
.101 - | .2 | $840 |
.201 - | .3 | $1,200 |
.301 - | .5 | $1,680 |
.501 - | 1.0 | $2,060 |
1.001 - | 2.0 | $3,600 |
2.001 - | 5.0 | $5,400 |
5.001 - | 10.0 | $8,400 |
10.001 - | 15.0 | $12,000 |
15.001 - | 30.0 | $16,800 |
30.001 - | 50.0 | $22,800 |
50.001 - | 100.0 | $28,800 |
>100.0 | $34,800 |
Annual flow fees are reduced by twenty percent (20%) for discharges that are comprised of greater than ninety percent (90%) of non-contact cooling water.