415 ILCS 50/3.01

Current through Public Act 103-1052
Section 415 ILCS 50/3.01

No person may establish, operate, manage or maintain any wastewater land treatment site or digested sludge utilization site within any county unless a program for that purpose is first submitted to a steering committee of 15 members appointed as follows:

(1) 5 members appointed by the County Board of the County within which the proposed site is located;
(2) 3 members appointed by the applicant;
(3) 2 members appointed by the President of the University of Illinois, at least one of whom shall be a representative of the local Agricultural Extension Service; and
(4) 5 members, including one appointed by the Director or Secretary of each of the following Departments:
(a) the Environmental Protection Agency;
(b) the Department of Natural Resources;
(c) the Department of Transportation;
(d) the Department of Public Health; and
(e) the Department of Agriculture.

415 ILCS 50/3.01

P.A. 91-357, eff. 7/29/1999.