105 ILCS 5/15A-30

Current through Public Act 103-1059
Section 105 ILCS 5/15A-30 - Small projects

In any case in which the total overall cost of the project is estimated to be $12,000,000 or less, the school district may combine the 2-phase procedure for selection described in Section 15A-25 into one combined step if all the requirements of evaluation are performed in accordance with Section 15A-25.

105 ILCS 5/15A-30

Added by P.A. 103-0491,§ 10, eff. 1/1/2024.