shall be exempt from the noise permit requirements of section 342F-4; provided that written notification of the intent to construct shall be submitted to the department by the person responsible for the construction project. The notification shall include information concerning the person responsible for the construction project, type of construction, location, and estimated duration of the construction project. The notification also shall include an acknowledgment that the construction project shall be subject to operational times and a maximum noise level of seventy-eight decibels when measured at any point at or beyond the property line of the construction premises.
provided that subsection (a) shall not apply to a construction project that emits noise exceeding seventy-eight decibels, regardless of the time of occurrence of the noise.
"Construction" means any or all activities including those activities necessary or incidental to the erection, demolition, renovation, or alteration of buildings.
"Dwelling" means a room or rooms connected together constituting an independent housekeeping unit for an individual or a family, and containing facilities for bathing, cooking, or both.
"Notification" means a formal notice to the department of the intent to construct a project exempt from noise permit requirements under subsection (a).
HRS § 342F-4.5