Haw. Rev. Stat. § 269-104

Current through Chapter 253 of the 2024 Legislative Session
Section 269-104 - Additional customer-generators

Notwithstanding section 269-102, an electric utility is not obligated to provide net energy metering to additional customer-generators in its service area when the combined total peak generating capacity of all eligible customer-generators served by all the electric utilities in that service area furnishing net energy metering to eligible customer-generators equals .5 per cent of the system peak demand of those electric utilities; provided that the public utilities commission may increase, by rule or order, the allowable percentage of the electric utility's system peak demand produced from eligible customer-generators in the electric utility's service area, whereupon the electric utility will be obligated to provide net energy metering to additional eligible customer-generators in that service area up to the increased percentage amount.

HRS § 269-104

L 2001, c 272 , pt of §6; am L 2005, c 104, §4 .